Excavation removes material from its natural position. In-place volume (“bank volume”) and loose, disturbed volume differ because soil can expand when excavated, a property represented here by Swell allowance.
In-place quantity and swell adjustment
V_{\mathrm{bank}}=LWHIn-place quantity and swell adjustment
In-place quantity and swell adjustment
Vb = in-place bank volume (m³); L/W/D = Length, Width and Depth (m); N = Quantity; Vl = loose volume (m³); s = Swell allowance (%). The calculator uses loose volume for truck-load rounding and optional handling price.
Measure the bank excavation and transport assumptions
| Mode | Exact visible fields (unit; defaults where supplied) |
|---|---|
| Rectangular excavation | Length (m); Width (m); Depth (m); Advanced: Quantity [default 1]; Swell allowance (%) [default 20]; In-place density (kg/m³) [default 0]; Truck capacity (m³) [default 0]; Handling price (/m³) [default 0] |
Calculate bank volume and loose material
Select Rectangular excavation. Measure Length, Width, Depth in meters, then set Quantity. Advanced inputs include Swell allowance (default 20%), In-place density (default 0 (optional)), Truck capacity (default 0 (optional)) and optional Handling price (per loose m³). Calculate to assess both excavation size and removal load.
Bank soil, loose soil and truckloads
Primary result: Loose volume to handle. Details include bank volume, loosened volume, in-place mass, truck loads rounded upward and optional handling cost. Truck capacity is in cubic meters of loose material; density applies to bank volume.
A trench is a measured rectangular prism
A 10 m × 2 m × 1.5 m excavation has bank volume 30 m³. Document separate trenches or multiply Quantity for identical pits.
A 10 m × 2 m × 1.5 m excavation has bank volume 30 m³. Document separate trenches or multiply Quantity for identical pits.
Swell changes transport requirements
With 20% Swell allowance, that 30 m³ bank volume becomes 36 m³ loose volume. This is the quantity to compare with truck capacity.
With 20% Swell allowance, that 30 m³ bank volume becomes 36 m³ loose volume. This is the quantity to compare with truck capacity.
Loads and ground safety are different questions
At 6 m³ per truck, 36 m³ requires 6 loads. Before excavation work, plan soil classification, utility location, access, protection, slope or shoring using the applicable safety rules.
Quick answers
What is bank volume?
The geometric quantity of soil before digging, calculated as length × width × depth × quantity.
Which volume is used for truck loads?
The loose volume after Swell allowance.
Why is density an input?
In-place density estimates the bank material’s mass.